Preparing to apply for your generation
We're here to support the sustainable energy transition, which is why we work with utility-scale renewable generation providers to connect generation to our high-voltage network wherever possible.
Contact us early in your planning process so we can work with you and your engineering consultant to provide guidance specific to your project.
To help you assess site suitability for your project, view our map to see hosting capacity to connect distributed generation to our high-voltage network, as well as areas of export congestion.
View map
Please note: The Firstlight Network area is not currently included on this map but will be added in early 2027. The map provides estimated hosting capacity and export congestion information only.
Getting your application underway
Discuss your proposed generation connection with us
Before submitting your application, you'll need to discuss your proposed generation connection with Powerco. Please complete our enquiry form so we can understand your requirements and arrange an initial discussion.
Ready to proceed with your initial application?
If you've already completed any pre-application enquiries and are ready to submit your application, please complete the initial application form.
Initial application form
Check that you have read all the supporting documents to help with your application, including the Congestion Management Policy which sets out the principles governing how Powerco will manage export congestion on its network.
An application fee of $7,690 (GST excl.) is applicable.
Once we've accepted your application, we'll respond within 30 business days with a review of connection options and requirements that your project will need to meet as it progresses. These requirements will vary depending on what development is required to safely connect your generation to our network, and whether Transpower involvement is needed.
We'll then confirm whether your initial application is approved and explain the next steps in the application process for your project.
Please see our utility scale distribution guide for an overview of the full connection approval process, which is designed to comply with the requirements of Part 6 of the Electricity Industry Participation Code.
If you have any questions, contact UtilityScaleGeneration@powerco.co.nz.
Our utility scale distributed generation application pipeline
Powerco publishes information on existing distributed generation applications of 300kW or more, forming our network connections pipeline. The pipeline report includes aggregated information on applications in process. Summary information on individual applications and their priority position in the pipeline is provided in the report accordance with the Queuing and management policy and clock stop/start mechanism for distributors.
View pipeline report